Completed: August 2020
Demo of Existing Bridge Structure
Bridge Reconstruction
Three Span 180 LF
TX 28 Girders
Reverse Curve Design
Relocation of Utilities & Bore Under Creek
Completed: April 2019
Two Span 130 LF
36" Slurry Shafts
Abutments
Columns
TX 40 Beams
Completion Date: December 2020
3,650 LF of 10' Wide Trail
106 LF Prefabricated Pedestrian Bridge
Colored Textured Concrete
8,000 LF of Quarried Limestone Blocks
Environmentally Sensitive Area
Completed: July 2018
100,000 CY Excavation
Reinforced Concrete Lining with Drainage
Water and Sewer Improvements
1,064 LF of 10'x12' Box Culverts
Sidewalk and Lighting Improvements
October 2019
Reconstruction of Three Bridges
Single Span 50 LF Slab Beam Bridge
Three Span 125 LF Slab Beam Bridge
Completed: January 2020
Three Span 558 LF
Steel Girders
Completed 20 Days Early
Completed: September 2018
Single Span 60 LF
Lined Channel w/ 18" Stone Riprap
Completed: October 2019
Reconstruction of Four Bridges
Five Barrel 10'x7' MBC (26 LF)
Two Span 80 LF Slab Beam Bridge
Single Span 40 LF Slab Beam Bridge
Five Barrel 10'x9' MBC
Completed: December 2020
Bridge Construction
Two Span 180 LF
TX 40 Concrete Girders
2,500 SQ FT of Sidewalk Bridge
384 LF of C411 Rail